25/01/2010 13:50:00

Aker Spitsbergen enters operations

During the weekend, Aker Spitsbergen left Norway's Klosterfjorden in

Sunnhordland community, for field deployment in the Norwegian Sea. The advanced

drilling rig arrived on site Monday morning, ready for drilling and well

operations at the Halten Nordland region, where Statoil is the operator.

Construction and completion of the rig have taken longer than anticipated. Under

the original contract, the rig was to be delivered and ready for operations in

February 2008. One year ago, it was announced that the rig would be ready for

operations in the summer of 2009. However, deployment is taking place in January

2010.

In August 2009, the rig formally began its contract with Statoil, following

protracted negotiations between Statoil and Aker Drilling regarding practical

and financial consequences of the delays, including liquidated damages for late

delivery, additional equipment costs, and day rates.

"Naturally, the delays and cost increases were disappointments. Now, however, we

at Aker Drilling are extremely pleased that Aker Spitsbergen has also commenced

operations. Finally, the rig's highly qualified crew can demonstrate their

skills at sea and prove just how safely and efficiently this sophisticated rig

will operate," says Geir Sjøberg, Aker Drilling's President and CEO.

Three and a half years to go

Once operations begin, about three and a half years remain of the five-year

contract confirmed by Statoil in April 2008. The oil company has exercised its

right to shorten the contractual period because of the delays. Statoil holds

options to extend the contract five times, each for a period of two years. The

agreed day rate during the option periods is higher than in the first five-year

period.

"Although the postponements and shorter charter period will reduce our fixed

drilling charter revenues, our goal, of course, is to make Statoil so satisfied

with the rig and its crew that the company will want to extend the drilling

contract. As we see it, demand will increase for deepwater rigs with our

specifications," says Mr. Sjøberg.

Upgrades

As early as in May this year, Aker Spitsbergen will again be wharfside. As part

of the August 2009 negotiations with Statoil, the parties agreed to upgrade the

rig in the second quarter of 2010. The upgrades will make the rig even more

efficient at subsea well completion work and other operations.

While the exact duration of the layover has yet to be determined, it will

presumably last between 6 and 10 weeks. During that period, various minor rig

improvements will also be made. No day-rate revenues will accrue during the

shipyard layover.

"We greatly appreciate the close cooperation we have had with Statoil during

construction and completion of the rig. Statoil could have opted to cancel the

contract, but instead chose to continue working with us. Our efforts are now

focused on operational excellence and making our rig the best on the Norwegian

continental shelf," says Geir Sjøberg.

This information is subject of the disclosure requirements acc. to §5-12 vphl

(Norwegian Securities Trading Act)

[HUG#1376873]

Popular news

LatestMost read
 

Post comment

Version: LiveBranchBuild_20100824.3 - EUROSRV22 - 2010-09-02 21:17:02 - 2010-09-02 20:17:02 - 3 - Website: OKAY